Navigating Public Right of Way (ROW) Parking Restrictions: What Contractors Need to Know

123 TCP • October 23, 2026

Share this article

Toy cars and road signs around a sketchbook with a pencil on a blue background

You have a job to do—whether it’s an underground dig, a sewer tie-in, or a crane lift—and the last thing you want is a delay caused by municipal red tape. We understand that acquiring an encroachment permit and managing public parking isn't your main goal; it's an administrative hurdle keeping you from breaking ground.


Securing the right to restrict parking in the public Right of Way (ROW) is a vital, yet increasingly complicated step. To help clear the confusion, we're breaking down the latest municipal trends and requirements, featuring insights directly from Adam, a leading voice in traffic control management.

The Permitting Maze: More Than Just an Encroachment Permit

Traditionally, the authority to block off parking was simply rolled into a standard encroachment permit. While that is still true in many jurisdictions, municipalities are tightening their grip.


As Adam recently noted in his Linkedin article:

"Depending on which agency owns the ROW, the process can become more complex than anticipated."

-Adam Freeland, Founder

Hidden Fees and Separate Applications

Increasingly, agencies are requiring a completely separate permit or application specifically for parking spaces. Contractors need to budget not just for the administrative cost of the permit, but for the space itself.


"It is common to have fees that compensate for both the agency's processing overhead, AND the parking/meter revenue the agency may lose from not having the spaces available," Adam explains.

The Evolution of "No Parking" Signs

Once your permit is approved, the physical signs must be placed. While a few helpful agencies will post the signs on your behalf, the vast majority push this responsibility onto you, the contractor.


Before you run to the hardware store for a permanent marker and a blank sign, beware of changing agency standards.

Moving Away from Handwritten Signs

"Increasingly, generic 'no parking' signs with hand-written specifics (date/time, etc.) are falling out of favor, with agencies leaning on fully printed signs," Adam warns.


Modern requirements often dictate that signs must be:


  • Fully printed to ensure legibility.



  • Weatherproofed (laminated or printed on waterproof substrates) to survive rain and environmental degradation.


  • Digitally integrated, with some agencies requiring QR codes that link directly to your active permit details.


  • City-furnished, meaning you may be required to purchase or lease specific signs directly from the municipality.

Timing Your Posting and Towing Eligibility

Getting the signs up is only half the battle; getting them up on time is what actually allows you to tow unauthorized vehicles and clear your work zone.


"48-72 hours is the most common minimum posting window," Adam notes. "Some agencies require more, and some, specifically in short-term metered areas, may require less."

Photographic Proof

You cannot just set the signs and forget them. Many local agencies now require a strict chain of evidence. To be eligible to have a vehicle towed from your work zone, you will likely need to furnish time-stamped photos to the agency proving the signs were correctly posted before the minimum time window began.

How 123TCP Keeps Your Project Moving

Before you can pull that encroachment permit or post those specialized parking signs, the city is going to demand a professional Traffic Control Plan (TCP). If you are already behind schedule, waiting weeks for a traditional contracting firm to draft a plan is out of the question.


That’s where 123TCP comes in.


We are a direct-to-drafter marketplace. We cut out the middleman, meaning you communicate directly with the experts drawing your plan. Because we don't sell physical signs, cones, or flagger services, our sole focus is getting your plan approved fast. We even offer expedited options to ensure a stalled project gets moving as quickly as possible.


Stop letting municipal red tape hold up your crew.

Frequently Asked Questions

  • Do I need a separate permit just to restrict parking?

    It depends entirely on the municipality. While parking restrictions are often included in a standard Encroachment Permit, many agencies now require a secondary permit specifically to account for the loss of public parking and meter revenue.

  • Can I use standard, store-bought "No Parking" signs and write the dates in marker?

    Increasingly, no. Agencies are moving toward strict standards that require fully printed, waterproofed, and sometimes QR-coded signs. Always check your specific encroachment permit requirements before fabricating or buying signs.

  • If someone parks in my permitted zone, can I tow them immediately?

    No. Most municipalities enforce a strict 48- to 72-hour minimum posting window. Furthermore, you will often need to provide the city with photographic proof that the signs were set up properly at the start of that window before they will authorize a tow.

  • Does 123TCP provide the physical "No Parking" signs or flaggers?

    No. 123TCP specializes exclusively in providing fast, accurate Traffic Control Plans (TCPs). By focusing only on the plans and connecting you directly with skilled drafters, we avoid upselling you on equipment and get your paperwork approved faster.

  • How fast can I get a Traffic Control Plan so I can apply for my permit?

    Because 123TCP is a direct marketplace, we offer highly competitive turnaround times, including expedited plan options for contractors who need to submit to the city immediately.

Recent Posts

By 123 TCP • October 30, 2026
Confused by the MUTCD and local city traffic regulations? Learn what you need for your encroachment permit and how 123TCP gets your plans drafted fast.
Person using a tablet beside a roadwork barrier, with a construction sign in the background.
By 123 TCP • September 29, 2026
Blindsided by a Traffic Control Plan requirement for your encroachment permit? Learn about generic, site-specific, and phased TCPs to keep your project on schedule.
Hand stamping a document on a desk, with a blurred laptop in the background
By 123 TCP • September 21, 2026
Learn what an encroachment permit is, why contractors need one for public right-of-way projects, and how 123TCP speeds up your Traffic Control Plan approvals.
Downtown street with orange traffic cones, cars, and a roadwork sign at dusk
By 123 TCP • September 10, 2026
Struggling to get your sidewalk closure or pedestrian diversion approved? Learn how to navigate municipal TCP requirements and get your permits approved fast.
Aerial view of a suburban four-way intersection with houses, trees, lawns, and parked cars.
By 123 TCP • August 31, 2026
Need a Traffic Control Plan for public right-of-way on private property? Learn how to navigate double the red tape, avoid delays, and get your TCP approved fast.
Worker in reflective gear walking on wet pavement carrying two orange traffic cones
By 123 TCP • August 16, 2026
Learn when to use lane shifting instead of full closures for your next construction project. Discover how proper taper lengths save time and flagging costs.
Toy cars and road signs surrounding a sketchpad with a drawn intersection on a blue background
By 123 TCP • August 4, 2026
Stalled by municipal permit red tape? Discover who your Traffic Control Plan is really for, avoid costly revision cycles, and get approved faster with 123TCP.